Safari Books Online is a digital library providing on-demand subscription access to thousands of learning resources.
exam answers Exam Questions 1. Answer: C Answers This is really a question about inputs and outputs. There's only one process that takes "requested changes" as an input, and that's Integrated Change Control. That's where your changes get approved. The other answers all refer to other processes: A is about Develop Preliminary Scope Statement, while B and D are both about Direct and Manage Execution. 2. Answer: B The preliminary scope statement is created in the Develop Preliminary Scope Statement process, which happens after Develop Project Charter. Develop Project Charter is the very first process on any project, and the inputs in answers A, C and D exist before the project started. The preliminary scope statement is created during the project. This is a "which-is-not" question. When you see a question asking you to choose which input or output is not associated with a process, one good strategy is to try to think of what it is that process does.