Name the outputs of the Monitor and Control Project Work process. The outputs are change requests (which include corrective action, preventive action, and defect repair), project management plan updates, and project document updates.
Name the processes that integrate with the Administer Procurement process. Direct and Manage Project Execution, Report Performance, Perform Quality Control, Perform Integrated Change Control, and Monitor and Control Risk.
Describe the purpose of the Report Performance process. Report Performance concerns collecting and distributing performance information about the project, including status reports, progress to date, and forecasts.
Name the purpose of the Perform Integrated Change Control process. Perform Integrated Change Control is performed throughout the life of the project and involves reviewing all the project change requests, establishing a configuration management and change control process, and approving or denying changes.