Safari Books Online is a digital library providing on-demand subscription access to thousands of learning resources.
1. D. Integration occurs when resources, equipment, or property are reassigned or redeployed back to the organization or to another project.
2. A. Starvation occurs because the project no longer receives the resources needed to continue. Resources could include people, equipment, money, and the like.
3. A. Extinction is the best type of project end because it means the project was completed successfully and accepted by the sponsor or customer.
4. C. The project manager is responsible for documenting the formal acceptance of the work of the contract. This should be done during Close Procurements when projects are performed under contract or during Close Project or Phase if no work was performed under contract. In cases where part of the work was performed under contract and part with in-house staff, formal acceptance should occur in both of these processes.