Chapter 6: Risk Planning > Review Questions - Pg. 282

282 Chapter 6 N Risk Planning Review Questions 1. You are a project manager for Fountain of Youth Spring Water bottlers. Your project involves installing a new accounting system, and you're performing the risk-planning pro- cesses. You have identified several problems along with the causes of those problems. Which of the following diagrams will you use to show the problem and its causes and effects? A. Decision tree diagram B. C. D. 2. Fishbone diagram Benchmark diagram Simulation tree diagram Assessing the probability and consequences of identified risks to the project objectives, assigning a risk score to each risk, and creating a list of prioritized risks describes which of the following processes? A. Perform Quantitative Risk Analysis B. C. D. Identify Risks Perform Qualitative Risk Analysis Plan Risk Management