Understanding How This Applies to Your Next Project
In my organization, the Plan Procurements process comes right after finalizing project scope because it takes a great deal of time and effort to procure goods and services. That means we have to start procuring resources as early in the project as possible in order to meet the project deadlines.
In all the organizations I’ve worked in, someone has always been responsible for procurement—whether it was a single person or an entire department. Typically, the procurement department defines many elements of the procurement management plan. Sure, the project team determines how many vendors need to be involved and how they’ll be managed along with the schedule dates, but many other elements are predetermined, such as the type of contract to use, the authority of the project team regarding the contract, how multiple vendors will be managed, and the identification of prequalified sellers.