The dashboard allows you to display project milestone variances using a bar chart
representation. To create the dashboard, we first create a milestones
list and then create a web part page displaying the chart.
Applying what you learned in Chapter 3, use the settings in Table 7-1 to create a
custom list called Project Milestones.
Table 7-1. Project Milestones custom list settings
Column
name
Type
Required
WBS
Number
No
Baseline
Finish
Date and
Time
No
Actual
Finish
Date and
Time
No
Create a new column called Variance with the following
settings:
Column Type: Calculated
Formula: [Actual Finish] - [Baseline Finish]