Exercises

1: This term refers to the greatest amount of time that can pass between a project’s start date and its finish date without affecting the end date of the entire project.
  1. Earliest start time

  2. Earliest finish time

  3. Latest finish time

  4. Latest start time

2: Match the following list of mathematical analysis techniques with their description given below: PERT, GERT, and CPM.

Used to identify the least-flexible activities in a project based on float calculations

Used to determine project duration based on three time estimates: optimistic, pessimistic, and most likely

Illustrates loops in the activity sequence, branches between activities, and different project outcomes




  

You are currently reading a PREVIEW of this book.

                                                                                                                    

Get instant access to over $1 million worth of books and videos.

  

Start a Free Trial


  
  • Safari Books Online
  • Create BookmarkCreate Bookmark
  • Create Note or TagCreate Note or Tag
  • PrintPrint