SECTION: III THE PROJECT MANAGEMENT KNOW... > PROJECT TIME MANAGEMENT - Pg. 129

6 CHAPTER 6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to manage timely completion of the project. Figure 6-1 provides an overview of the Project Time Management processes, which are as follows: 6.1 Define Activities--The process of identifying the specific actions to be performed to produce the project deliverables. 6.2 Sequence Activities--The process of identifying and documenting relationships among the project activities. 6.3 Estimate Activity Resources--The process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity. 6.4 Estimate Activity Durations--The process of approximating the number of work periods needed to complete individual activities with estimated resources.